You can use Project Start Date and rebase all project task based on their duration or existing start and end time.


  1. Navigate to edit project you want to rebase omniWorks \ Projects, select Edit.
  2. Select Schedule section.
  3. Configure a new project start date.
  4. Optionally select Send Email or Send SMS update or both. If send update is selected, once task is rebased, an update will be send to a task workflow .
  5. Click Rebase Project Tasks.